Construction of Ksh.20 billion Mwache dam to begin this November

The construction work of the much-awaited Ksh.20 billion Mwache Multipurpose Dam project in Kwale County is set to begin next month.

The project whose contract was signed in August 2018 was delayed for several years as the constructor awaited the government to finalize the land compensation exercise.

Addressing the press in Kwale County, Permanent Secretary (PS) for Water in the Ministry of Water, Sanitation and Irrigation, Joseph Irungu said, the government has finally made a breakthrough in the construction of the dam.

Irungu added that the government is working hard to ensure that all issues that have delayed the project including land compensation are finalized before November 1, 2021.

“The government has sent money to the National Land Commission to finalize the compensation exercise and we expect the commission to complete the exercises so that we can hand over the order of commencement to the contractor,” Irungu said.

The area Governor Salim Mvurya says a total of Ksh.4 billion shall be used to compensate individuals who will permanently lose their parcels of lands to the mega dam project.

The government announced that over 77 percent of persons living in critical areas where the main dam shall be constructed have already been compensated.

The compensation exercise is expected to hit 90 percent by next week as the National Land Commission (NLC) is set to expedite the disbursement of funds.

The project will require 1,600 acres of land and will involve displacement of approximately 12,000 persons whose assets and livelihoods may be affected, as well as access to natural or economic resources as a result of activities under the Mwache Dam Project.

The seven-year project co-funded by the World Bank and the Kenya Government through Kenya Water Security Programme is expected to eradicate the problem of water shortage in the counties of Kwale, Mombasa, and Kilifi.

“In partnership with the Ministry of Water, Sanitation and Irrigation and NLC we have achieved significant progress in acquiring the priority land required which will allow the issuance of order to commence works in November this year,” said Mvurya.

The Dam is located across the Mwache River at the Fulugani village in Kinango Sub-County in Kwale County.

The Mwache Dam development project under the portfolio of the Ministry of Water, Sanitation, and Irrigation is a significant investment by the National Government as a flagship project under the Vision 2030.

Governor Mvurya expressed his gratitude to the national government for bringing in key projects in the county.

“I want to reaffirm my support for this project that will not only sustain our region of domestic water supply but also promote agribusiness in the region,” said the Governor adding that the dam will help residents who have been ravaged by drought over the decades.

‘‘We support this project wholeheartedly. We are very happy because this project will refurbish and replenish the economy of this county,’’ Mvurya said.

The Mwache Dam is an 87.5-meter-tall concrete gravity dyke, impounding 118 million cubic meters of water with a daily supply of 186,000 cubic meters of water.

The massive dam once complete is also expected to put 2,600 hectares of land under irrigation in Kwale County and address the food shortage experienced in the county.

The project will change the economy of the coastal region with PS Mvurya saying coprporation between National Governemt and devolved units was key to achieve Kenya’s 2030 economic goals.

“We thank the county government for their support in ensuring that we have reached this milestone. It’s through this cooperation that will make government projects successful” said the PS who was accompanied by NLC Commissioner Kazungu Kambi and Adrian Cutler, a representative from the World Bank.

Also Read:

  1. Agency in dams contracts to pay KRA Ksh.643 million
  2. Rotich’s prosecution in Ksh63 billion dam scandal postponed
  3. Uhuru orders immediate cancellation of Ksh22 billion Kimwarer dam, okays Arror

The project will produce 186 million cubic liters per day to supply Kwale and Mombasa counties’.

Mwache dam is a project crafted in line with the big four agendas of President Uhuru Kenyatta to address the problem of water shortage and improving the country’s food security.

A visit to the site showed that Coast Development Authority (CDA) has completed activities around the project site such as tree planting, terracing, contour plowing, rock terracing, gabion construction, and marking and pegging.

Kambi said the commission is at the peak of finalizing issues of land compensation adding that the commission has received funds from the Ministry of Water, Sanitation, and Irrigation and it will be channeled to the residents who await compensation with bated breath.

The NLC commissioner, a former Kaloleni MP and Labour Cabinet Secretary said compensation for 36 graves would be completed by next week.

“As I speak, don’t be surprised to hear that the residents have received their money. The commission is keen to ensure that by next week, 99 percent of residents are compensated,”Kambi said.

Kambi asked the coastal residents to support the government’s projects to change their livelihoods.

”The government has invested heavily in the coastal region and it’s time to appreciate the effort made by President Uhuru Kenyatta,” Kambi added.

The commissioner recognized the World Bank for its support in changing the lives of the people of Kwale and the entire nation.

With input from AgencY (KNA)